Thanks go out to Darrel for replacing the fluorescent light fixture in the middle bathroom. (It's always good to see where you are going…!)
Annex–The landlord did repair the swamp cooler on the east side of the annex, and there are now two functional swamp coolers in the annex.
Roof leak at swamp cooler over the metal shop drill press–The landlord notified me that the roofer would pull the cooler and do the roof repairs on Saturday, about 3 weeks ago. Any evidence to the contrary?
Moved the paint spray booth from the metal shop to the covered portion of the north side fenced area.
All spray paint/coatings were moved from the paint spray booth and laser cutter room lockers to the gray metal cabinet in the north side fenced area.
Moved a large quantity of stored chip board and other lumber from the north side fenced area to the locked fenced area adjacent to the annex roll up door. (Material had been stored in excess of 30 days w/o a renewal of the Project Parking Permit.)
“Slimed” (the trademarked green tire sealant) two hand cart tubeless tires which seem to always go flat. (There are other options, including a novel one that Jesse T. described, if they continue to fail to hold air).
Relamped the fluorescent light fixture in the southwest corner of the Fiber Arts room.